The project work entitled Construction of 4 Lane (2x2 Lane) High Level Bridge Across River Satluj Cross Ropar by pass in KM-2 Phese-2 in Dist. Ropar & SBS nagar as per the requirements of project semester for the award of degree of B.E. (Civil Engineering), DBFGOI , Moga under the guidance of Mr. Perveer Rathod and Mr. Narvir Singh, during Dec 2013 to June 2014).
Financial statement of our construction project
Project name- Construction of high level bridge over River Satluj ( Distt. Ropar )
Name of Client- P.W.D(B&R)
Name of Contractor- SP SINGLA CONSTRUCTIONS PRIVATE LIMITED PANCHKULA
Designer of project- B& S Engineering Consultants Noida
Duration of project- 2 YEARS
Commencement of Project – feb 2013
Ending of project- Feb 2015
Estimated cost- 70 Crores
Division of money-:
Operatrion of office……………………………………0.5%
Drawings………………………………………………0.5%
On casting of well curb and Coffer Dam……………...2.3%
Casting of well…………………………………………14%
Sinking of wells……………………………………….5%
Plugging……………………………………………….2.8%
Well Cap……………………………………………….2.25%
Substructure
Pier/Abudment/Return Wall……………………………2.5%
Respective Caps………………………………………..2.5%
Bearings………………………………………………...1.5%
Backfilling ……………………………………………..1%
Superstructure
Casting of Girders……………………………………….13%
Pre stressing and grouting………………………………..2%
Deck slabs…………………………………………………11.5%
Construction of approaches ……………………………………..7%
Protection work…………………………………………………..30.9%
TOTAL…………………………………………………………….100%
TOTAL COST……………………………………………………70 CRORES