16-11-2012, 05:49 PM
NYC DEPARTMENT OF TRANSPORTATION DIVISION OF BRIDGES
NYC DEPARTM.ppt (Size: 8.93 MB / Downloads: 157)
EAST DRIVE OVER EAST WOOD ARCH
IMPLEMENT WORK ZONE PEDESTRIAN TRAFFIC CONTROL PROVISIONS
REPAIR STONE MASONRY
REPAIR CRACKS AND SPALLS IN FASCIA
TUCK POINT BRICK FACING
REPLACE UNDERDECK LIGHTING FIXTURES
WEST 181ST STREET RAMP TO GW BRIDGE
IMPLEMENT WORK ZONE TRAFFIC CONTROL PROVISIONS
REPAIR UNDERDECK SLAB
REMOVE AND REPLACE 75 mm OF ASPHALT OVERLAY ON BRIDGE DECK
CONSTRUCT NEW CURBS, SIDEWALKS, BRIDGE RAILING, AND CORRUGATED GUIDE RAIL WITHIN PROJECT LIMITS
REPLACE UNDERDECK LIGHTING FIXTURES
REINSTALL PAVEMENT STRIPING AND PAVEMENT EMBEDDED TRAFFIC LOOPS
JACKIE ROBINSON PARKWAY OVER AUSTIN STREET
IMPLEMENT WORK ZONE TRAFFIC CONTROL PROVISIONS
REPAIR UNDERDECK AND ABUTMENTS
REPLACE ASPHALT PATCHING LOCALLY
REPLACE DECK JOINT