Project work entitled Construction of 4 Lane (2x2 Lane) High Level Bridge Across River Satluj Cross Ropar by pass in KM-2 Phese-2 in Dist. Ropar & SBS nagar as per the requirements of project semester for the award of degree of B.E. (Civil Engineering), DBFGOI, Moga under the guidance of Mr. Perveer Rathod and Mr. Narvir Singh, during dec 2013 to June 2014).
Financial statement of our construction project
Project name- Construction of high level bridge over River Satluj ( Distt. Ropar )
Name of Client- P.W.D(B&R)
Name of Contractor- SP SINGLA CONSTRUCTIONS PRIVATE LIMITED PANCHKULA
Designer of project- B& S Engineering Consultants Noida
Duration of project- 2 YEARS
Commencement of Project – feb 2013
Ending of project- Feb 2015
Estimated cost- 70 Crores
Division of money-:
Operatrion of office……………………………………0.5%
Drawings………………………………………………0.5%
On casting of well curb and Coffer Dam……………...2.3%
Casting of well…………………………………………14%
Sinking of wells……………………………………….5%
Plugging……………………………………………….2.8%
Well Cap……………………………………………….2.25%
Substructure
Pier/Abudment/Return Wall……………………………2.5%
Respective Caps………………………………………..2.5%
Bearings………………………………………………...1.5%
Backfilling ……………………………………………..1%
Superstructure
Casting of Girders……………………………………….13%
Pre stressing and grouting………………………………..2%
Deck slabs…………………………………………………11.5%
Construction of approaches ……………………………………..7%
Protection work…………………………………………………..30.9%
TOTAL…………………………………………………………….100%
TOTAL COST……………………………………………………70 CRORES
Financial statement of our construction project
Project name- Construction of high level bridge over River Satluj ( Distt. Ropar )
Name of Client- P.W.D(B&R)
Name of Contractor- SP SINGLA CONSTRUCTIONS PRIVATE LIMITED PANCHKULA
Designer of project- B& S Engineering Consultants Noida
Duration of project- 2 YEARS
Commencement of Project – feb 2013
Ending of project- Feb 2015
Estimated cost- 70 Crores
Division of money-:
Operatrion of office……………………………………0.5%
Drawings………………………………………………0.5%
On casting of well curb and Coffer Dam……………...2.3%
Casting of well…………………………………………14%
Sinking of wells……………………………………….5%
Plugging……………………………………………….2.8%
Well Cap……………………………………………….2.25%
Substructure
Pier/Abudment/Return Wall……………………………2.5%
Respective Caps………………………………………..2.5%
Bearings………………………………………………...1.5%
Backfilling ……………………………………………..1%
Superstructure
Casting of Girders……………………………………….13%
Pre stressing and grouting………………………………..2%
Deck slabs…………………………………………………11.5%
Construction of approaches ……………………………………..7%
Protection work…………………………………………………..30.9%
TOTAL…………………………………………………………….100%
TOTAL COST……………………………………………………70 CRORES