21-03-2012, 02:59 PM
Guide Lines for preparation & submission of training report
PREPARING_TRAINING_REPORT_2.pdf (Size: 15.43 KB / Downloads: 34)
Power Scenerio in India:
a) Present Installed capacity.
b) Present Per capita consumption, shortages.
c) Growth rate in installed capacity & per capita consumption. Regional Grids
in India.
d) Concepts of Availability Based Tariff (ABT)
e) Future additions proposed ( 11th 12th & 13th plans)
f) Future power plants (SC, USC, FBC, IGCC etc.)
3. Brief history of Panki TPS (with brief of UPRVUNL, which may be
downloaded from web site www.uprvunl.org).
4. Details of installed Units (Date of installation / deletion / de-ration / make of
Boilers – Turbines - Generators) at PTPS.
5. Organisational setup of Panki TPS.
6. General arrangement for a sub critical coal fired power generating unit.
7. Power generation at PTPS, Panki.
Units type, design, conventional - sub critical units
Raw material, coal, oil, water, air, chemicals.
8. Basic Cycles at PTPS:
i) Boiler layout
ii) Steam- reheat and superheat cycle
iii) Air cycle
iv) Pulverization of coal & pulverized coal feeding system
v) Condensate and feed water cycle
vi)Ash handling and disposal
9. Water treatment at PTPS and its need
Properties of DM water required
Need:
Boiler tube leakages-: blow down minimization
Scale formation- reduced heat transfer
10. Coal Handling at Panki TPS
11. Electrical / Elex / EI / EE students may skip sl. no. 9 & 10 above and
incorporate Details of Electrical LT / HT Motors, Switch Gears,
Generators / transformers at PTPS. Line diagram of Bus Bars / Switch
Yard / Control & Instrumentations / Auto Loops.
11. Envirnmental impacts (environmental concerns) of coal fired generation:
Coal reserves based on present availability and rate of exploration may
lasts for World average:190 yrs India:230yrs
CO2 emissions NOx / SOx / FGD etc.
Future measures:
a) Future High efficiency plants (USC/SC)
b) CO2 sequestration.
PROJECT DETAILS / Specific works carried out at divisions.
(Separate Section)
12. Conclusion:
Achievements, Observations, Measures being taken at Panki TPS (for
performance improvement / environmental protection / future expansion), To
be taken for any improvement ( suggestions) / Any other.