R0AD CONSTRUCTION MANKAPUR (GONDA) UNDER THE PROGRAM(PMGSY)
Summer Training Report.pptx (Size: 2.78 MB / Downloads: 65)
ABOUT THIS SUMMER TRAINING
This summer training about construction of all weather road in Mankapur (GONDA). We were working under Rural Engineering Department (RED). The head office of RED is situated at JAWHAR BHAWAN, LUCKNOW.PMGSY is controlled by RURAL ENGGINEER DEPARTMENT. Fund is given by national government of India. It is link road between MANKAPUR and GONDA.
ABOUT RURAL ENGINEERING DEPARTMENT (R.E.D)
The department was created by U.P. Government to strengthen Rural Infrastructure in the year 1972 administratively controlled under Ministry of Rural Development. This department mainly executes the construction works on deposit basis and is providing technical guidance to district and block level administrative officers as & when required
Introduction Mankapur (GONDA)
Our site is Mankapur village in GONDA district. Our site is Mankapur is a town and a nagar panchayat in Gonda district in the Indian state of Uttar Pradesh . It has Gonda to its west, has Rehra in its north, Maskanawa in the east and Nawabganj in the south. The birthplace of lord Rama, Ayodhya is only 37 km from Mankapur in south and well connected by rail and road network . Mankapur had a population of 8865
Mankapur is well connected by roadways to Gonda, Faizabad and state capital Lucknow
The length of road undertaken is 2 km
PURPOSE FOR preferring this site:
This road gets connected with Faizabaad road on one side & on the opposite side it get connected to MASKANVA via Rehra in its north village& many others.
It became as a shortcut route from Rama, Ayodhya is only 37 km road with only and Nawabganj in the south.
Without this route the distance from Ayodhya is 48km.
Without this route the distance from Nawabganj to Maskanawa & then to Faizabaad road is up to 15km of distance. Hence it totally saves time, money & distance.
WORK BEFORE MY SUMMER TRAINING
Analysis of need of new road on Mankapur village.
Government order for conduction of road on Mankapur district Gonda.
Survey on site new road .
Estimating & costing for the project.
Prepare budget for project.
Work on site begin on MAY LAST WEEK (23rd OF MAY
CONCLUSION
Conclusion is that this training was beneficial for us.
We have a lot of experience about road type and its characteristics as well as village road connection.
We have knowledge Indian road cods .
We have knowledge about Pradhan Mantri Gram Sadak Yojana.
We have knowledge about RURAL ENGINEER DEPARTMENT (RED).
We have knowledge about village road condition.
We have knowledge about road construction material like SOIL &