1. Discuss the improvements that can be applied to the software cost model? [16]
2. Describe the various dimensions of scheduling? How dimensions are helpful in
improving software economics? [16]
3. Provide the software development plan (SDP) outline? [16]
4. Describe the cultural issues raised in allowing online review of the native informa-
tion source by using smart browsing and navigation tools. [16]
5. (a) Define WBS. Describe conventional WBS issues.
(b) What are default agendas for the life-cycle architecture milestone? Explain.
[16]
6. Explain the following:
(a) Software architecture team
(b) Software development team. [8+8]
7. Team A found 342 errors during the software engineering process prior to release.
Team B found 184 errors. What additional measures would have to be made for
projects A and B to determine which of the teams eliminated more efficiently?
What metrics would you propose to help in making the determination? What
historical data might be useful? [16]
8. (a) Explain continuous integration.
(b) Give the context of CCPDS-R.